Today, work commenced on the Denison Avenue rehabilitation project. This project will reconstruct Denison Avenue between Ridge Road and West 25th Street, and along West 62nd Street from Denison Avenue to Barberton Avenue.

construction1

In addition to the pavement rehabilitation, the project will include the installation of a Cleveland Public Power underground power line duct bank, utility relocations, pavement reconstruction and resurfacing, curb sidewalk and driveway repairs. Advance notice signs will be posted to advise traffic of the detour.

The construction cost is $9,068,852.93. This project is scheduled for completion in December 2015. Additional traffic notices will be issued as work progresses.