Warner Road Rehabilitation Project

On Monday, February 1, 2016, work will commence on the Warner Road Rehabilitation Project. During this time, one lane of traffic in the southbound direction will be maintained between Grand Division Avenue and Broadway Avenue.

construction1

Northbound traffic will be detoured east along Grand Division Avenue then north along Turney Road.

Driveway access will be maintained at all times.  Motorists will need to be alert for lane shifts and barrels used to direct traffic. The Warner Road Rehabilitation project is scheduled for completion in December 2016.

The project extends along 0.8 miles of Warner Road from Grand Division Avenue to Broadway Avenue. Improvements made to Warner Road will include asphalt milling, pavement base repair, asphalt resurfacing, installation of ADA compliant ramps, water main installation, and new pavement markings.

The construction cost is $2.4 million.

About Dan Williams

Director of Media Relations for Mayor Frank G. Jackson, City of Cleveland

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s