The Division of Streets has recently begun transitioning road repair efforts to focus on residential neighborhood streets. The Division is currently operating 5 Pothole Killers and 10-12 hot asphalt repair crews per day, depending on the weather. …
Tag: Division of Streets
Division of Streets Pothole Repair Update (04/21/2014)
Below is a list of pothole repair completions and those repairs currently in progress for April 21, 2014. One Dura patch repair crew and nine hot asphalt repair crews were on duty. Repair Completions: East 40th Street …
Read More "Division of Streets Pothole Repair Update (04/21/2014)"
Division of Streets Pothole Repair Update (04/16/2014)
Below is a list of pothole completions and repairs currently in progress for April 16, 2014. Eleven hot asphalt repair crews and two Dura patch repair crews were on duty. Repair Completions: East 36th Street (St. Clair …
Read More "Division of Streets Pothole Repair Update (04/16/2014)"
Division of Streets Pothole Repair Update (03/25-26/2014)
Below is a list of pothole completions and repairs currently in progress for March 25-26, 2014. Ten hot asphalt repair crews and two Dura patch repair crews were on duty. 88 tons of hot asphalt …
Read More "Division of Streets Pothole Repair Update (03/25-26/2014)"
Chester Ave Resurfacing Project – Phase II Work
Effective Monday, March 31, 2014, construction will begin, weather permitting, on Phase II of the resurfacing project along on Chester Avenue between East 13th Street to East 27th Street. During this phase, the eastbound …
Division of Streets Pothole Repair Update 03/20/2014
Below is a list of pothole repair completions and repairs currently in progress for March 20, 2014. Eleven hot asphalt repair crews and two Dura patch repair crews were on duty. Repairs In Progress: …
Read More "Division of Streets Pothole Repair Update 03/20/2014"
Division of Streets Pothole Repair Update 03/19/2014
Below is a list of pothole repair completions and repairs currently in progress from March 19, 2014. Eleven hot asphalt repair crews and two Dura patch repair crews were on duty. Note: One of …
Read More "Division of Streets Pothole Repair Update 03/19/2014"
City Hires “Pothole Killer” to Address Problematic Streets
The Department of Public Works has entered into a contract with Patch Management, Inc. to assist with the repair and patching of potholes throughout various locations in the City of Cleveland. The approved contract …
Read More "City Hires “Pothole Killer” to Address Problematic Streets"
Division of Streets Pothole Repair Update 03/07/2014
Note: 8 crews utilized hot asphalt repairs and 2 crews utilized cold patch repairs today, March 6, 2014 Repairs in Progress: Broadview Road (Spring Road to Brookpark Road) Prospect Avenue (East 9th Street to …
Read More "Division of Streets Pothole Repair Update 03/07/2014"
Division of Streets Pothole Repair Update 03/06/2014
Note: 8 crews utilized hot asphalt repairs and 2 crews utilized cold patch repairs today, March 6, 2014 Repairs in Progress: Broadview Road (Spring Road to Brookpark Road) North Marginal Drive (West 98th Street to …
Read More "Division of Streets Pothole Repair Update 03/06/2014"